Dear Residents,

Welcome to the eleventh edition of our fortnightly newsletter.


Update On Works

You may or may not have noticed but Tony Phillips our Site Manager has taken a temporary leave of absence and in his place I would like to introduce you to Steven Smith who will be covering Tony until his return. Steven’s contact details are on the left of this page along with his photo. Welcome Steven.

We are happy to report that although we lost some days due to heavy rain late last month, we are on course to catch up with our current work schedule, and will endeavour to complete the works in August to programme.

Please see below our updated schedule of our balustrade replacement programme.

Block 150 - 180

Private balconies have been replaced.

The communal balconies have been replaced.

Block 246 - 268

Private balconies have been replaced.

Replacement of the communal balconies will commence as of Tuesday 1st July 2014.

Block 334 - 356

Commencing Thursday 26th June.

Block 358 - 380

Commencing Thursday 19th June.

Block 382 - 404

Commencing from Thursday 19th June.

Works to each block will take approximately 1 week to complete.


Come and Meet the Project Team

Our next Drop - In is:

Wednesday 16th July between 16.30pm – 19.30pm.

We look forward to meeting you then.


Respite Facility

Should you wish to take a break, please make use of our respite facility that is available to you at the rear of Block 382 – 404 Wood Vale.


Please see below percentage progress of the works.

The percentages have still not changed much for communal decorations and concrete repairs. This is because as stated previously, the work is subject to the completion of the balustrade installations.

Block 150 – 180 Wood Vale
Work% Complete
Scaffold erection 95%
Brickwork & Pointing 100%
Render repairs 100%
Concrete repairs 85%
Jet washing 100%
Communal decorations 95%
Block 182 - 244 Wood Vale
Work% Complete
Scaffold erection 95%
Concrete repairs roof 95%
Render repairs 100%
Concrete repairs 85%
Jet washing 100%
Communal decorations 95%
Block 246 - 268 Wood Vale
Work% Complete
Scaffold erection 95%
Material hoist / rubbish chute 100%
Pitched roof replacement 100%
Pre-Works inspection 100%
Brickwork / pointing 100%
Render repairs 100%
Concrete repairs 95%
Jet washing 100%
Communal decorations 90%
Block 270 - 332 Wood Vale
Work% Complete
Scaffold erection 95%
Concrete repairs roof 95%
Render repairs 100%
Concrete repairs 85%
Jet washing 100%
Communal decorations 90%
Block 334 - 356 Wood Vale
Work% Complete
Scaffold erection 95%
Material hoist / rubbish chute 100%
Pitched roof replacement 100%
Brickwork / pointing 100%
Render repairs 100%
Concrete repairs 90%
Jet washing 100%
Communal decorations 95%
Block 358 – 380 Wood Vale
Work% Complete
Scaffold erection 95%
Brickwork / pointing 100%
Render repairs 100%
Concrete repairs 90%
Jet washing 100%
Communal decorations 90%
Block 382 - 404 Wood Vale
Work% Complete
Scaffold erection 95%
Brickwork / pointing 100%
Internal fabric repairs 100%
Concrete repairs 90%
Jet washing 100%
Communal decorations 90%
 

Thank you all for your patience and co-operation.