Following on from our last Newsletter, bringing you up to date with what has happened so far.

Block 1-29 Sheenewood,

Scaffolding is completed and in place.

Window surveys have now been completed.

Concrete repairs are almost complete.

Brickwork repairs at ground level will be carried out when the scaffolding  is removed.

Replacements of fascia & soffits have been completed.

Rain water goods have been completed.

Roofing is now complete.

Window installations have started, but are running a couple of weeks behind the programme. This is due to design adaptions following the pilot installation.

Decorations to communal area commenced at the end of August and is now currently running to programme with completion date on target for September.

Block 14-44 Sheenewood

Scaffolding is in place.

Window surveys have all been carried out.

Brickwork and concrete repairs are 90% completed and on schedule.

Replacements of fascia & soffits have been completed ahead of schedule. Rain water goods works are due to start mid September.

Roofing is 95% complete and slightly ahead of schedule.

Window installations have started and are ahead of schedule.

Decorations have started ahead of schedule.

Block 46-72 Sheenewood

Scaffolding commenced, albeit later than anticipated. This was due to a shortage of labour during the summer holiday period which has now been addressed and the workforce has been increased. This may cause some delay to the completion date, however we will endeavour to make up for this time where possible and keep you updated.

Window surveys are approximately 90% complete.

Block 2-12 Sheenewood

Scaffolding is completed and in place.

Window surveys have started and are approximately 25% complete.

Brickwork and concrete repairs have started, slightly ahead of schedule.

 

Upcoming Events For Your Diary

Valentine Court & Sheenewood Residents Fun Day On Saturday 17th September 2016.

Time: 11am to 2pm

Place: Green Space Behind Breyer Group Compound

Valentine Court, Perry Vale, SE23 2JA

Come and join in - Enjoyment and fun to be had for everyone

Bouncy Castle, Face Painting, Children’s Entertainer, Drawing Competition, Free Refreshments & Free Raffle with Quality Prizes on the day

* * * * * * * * * * * *  * * * * * * * * * * * *  * * * * * * * * * * * *  * * * * * * * * * * * *  * * * * * * * * * * * *  * * * * * * * * * * * *  * * * * * * * * * * * *  

Sheenewood Drop In On Tuesday 20th September 2016

Time: 10am to12 midday 

Place: Breyer Group Site Compound behind the garages, on Sheenewood Estate.

Enjoy a nice cup of tea or coffee, biscuits & conversation with your RLO and  Project Officer.

We look forward to seeing you.

 

Should you have any questions or queries during the course of our works, your first point of contact is your RLO: Carole McGhie, She will be happy to help you, please do not hesitate to call her.

Security Reminder

All operatives will carry authentic ID Badges, clearly displaying the blue Breyer Group logo, the operative’s name, role  and will also contain a photograph of the operative. If in doubt of a contractor’s identity, please contact your RLO or Site Manager immediately. 

 

 

 

 


Share

Here to Help...

Carole McGhie

Carole McGhie

Resident Liaison Officer

07816 225 940

 

Steve Gracie

Steve Gracie

Site Manager

07977 510 154

Our site team are available between 8.00am and 5.00pm Monday to Friday should you have any questions or queries.