    Tower Hamlets Homes EWI Scheme


    Client: Tower Hamlets Homes
    Value of Works: £1,800,000
    Delivery: Single Delivery Period
    Location: Multiple Site – 19 Residential Blocks on the Avebury Estate, Turin Street, London, E2
    Form of Contract: NEC 3 incorporating June 2006 and September 2011 amendments
    Duration:48 weeks 2 days

Back

Description of Works: Breyer Group are currently undertaking Direct Fix External Wall Insulation works to 19 occupied residential blocks on the Avebury Estate, London, E2.

The Rockwall System we are using is REDArt Silicone 15/5207. This system involves sticking then mechanically fixing Rockwall insulation bats to the external walls. The next part of the operation is to apply a 3 coat render system to the bats using mesh in-between coats to prevent cracking. The final coat of render is a coloured coat that can be mixed to a vast range of colours and applied with a number of different finishes ranging from very smooth to stippled.

 

The Planning Department in Tower Hamlets decided that Eversley House and Rapley House should not have brick slips fitted to the ground floor so were rendered to the bottom of the block.

 

The remaining 17 blocks are to have individual brick slips fitted from the REDArt Brick Effect system.

 

Works also include:-

 

  • Installation of new double glazed windows
  • Decoration of existing Juliette balconies
  • Installation of extended window sills – some PVC

and some aluminium

  • Re-positioning of soil pipes and rainwater down pipes
  • Re-site all ariels and satellite dishes
  • Extension of boiler flues, condensing pipes, overflow pipes
  • Re-location of external lighting

Current: We are currently completing EWI at 14 blocks on the Avebury Estate which is taking on average 15 weeks per block from scaffold erection to the completion of installation of the brick slips.

Forthcoming: We have 3 blocks still to commence which are awaiting the erection of scaffolding

Whether Works Carried out Using Subcontractors or Direct Resources: On this EWI scheme we used specialist subcontractors who are Rockwool Approved Installers – Inex Home Improvements Limited and Apolodor Limited.

Evidence of Satisfaction Completion: Please see attached EWI Warranty Authorisation Form issued by Rockwool.

Guarantee Provider: Kinnell ECO

Evidence of Performance Achieved: Please see below

Funding: EDF Funded through the Client - Tower Hamlets Homes

Site Supervisor: Mark Smith

Site Manager: Colin Shepherd

Project Manager: Danny Nicholls

Contracts Manager: Spencer Marshall

Percentage of annual turnover project represented: 

17.4% of the annual turnover for the Tower Hamlets Homes contract

1.8% of the annual turnover of Breyer Group as a whole